Re: Ringwood Project - Installation of new points





Notagunzel wrote:

> I'm lead to believe that the existing pointwork at the Up end will be
> decommissioned (spiked & clipped etc) on Fri/Sat 19/20th, with levers etc,
> being sleeved & detection designed out of the control circuits.  Rodding etc
> is to be removed on this weekend as well.  The turnouts will be replaced the
> following weekend 27/28, with the new pointwork remaining spiked out until
> the commissioning of the new CBI on a date that I know not.

What is a CBI. I guess you mean Computer Based Interlocking which is a
non-official term.
Solid State Interlocking is the official term. (SSI)

>
>
> P.S. What is a RBM Turnout?

Dunno

>
>
> BC