Broadmeadows Upgrade
June 24th 2000 - December 2000
NEW >> Completed
Works
New
Signaling Operational SAT 18th - SUN 19th November 2000
Second set of points SAT 11th - SUN 12th
November 2000
October 2000
Update
September 2000 Update
Broadmeadows
Shutdown SAT 24th - SUN 25th June 2000
Photos
of Broadmeadows before works began 23rd June 2000
Summary
of works to be completed
For more information, see Chris Gordon's Broadmeadows
resignaling page.
Summary
of Works to be completed
Following info courtesy Chris
Gordon
Two sets of new
high speed points will be installed to allow Country VLP trains to run
into Platform 2 on Down (outbound) runs, all points will also be
motorised.
Other improvements will include upgrading of
mechanical signals to modern LED signals, and the installation of VDUs
to replace the current mechanical frame. The commissioning of
re-signalling is 23rd December (but maybe be brought forward to
November).
Signalling diagram showing
works to be undertaken:
map courtesy Chris
Gordon |
Chris's map description:
The
signals are a guess of what will be there, and I am not sure if
sidings 'C' will be staying.
The new layout
will be the same as now except points 11 (see map) will be
upgraded to high speed points, and a new set of high speed points
will be installed near the bridge for train from Melbourne to have
direct access to No.2 road (Up platform).
So in effect the
extra move will be that country and goods train going towards
Seymour will be able to use high speed points and No.2 road over
taking any 'spark' in No.1 road waiting to return to Melbourne.
This will eliminate the need to shunt the 'sparks' into the siding
for goods and country trains as is done now. |
Photos
of Broadmeadows before works began
Friday 23rd June 2000
 |
Looking North from
Platform 2.
23-06-2000 |
 |
Looking South from
Platform 2 showing where the new points will be installed.
23-06-2000 |
Broadmeadows
Shutdown
Saturday 24th - Sunday 25th June 2000
Works began on
Saturday 24th June, with a complete shutdown, affecting train services
on all Broad gauge lines north of Broadmeadows. Suburban trains terminated at Essendon, and services
were replaced with busses
from Essendon to Broadmeadows. As services terminated at
Essendon, platform 1 was used, it sees no regular
service these days.
Freight trains ran prior to the weekend in the North East, as a
result of the shutdown. The spark
transfer was cancelled.
Points at the southern
end were installed on Saturday, and the overhead modified on
Sunday. No special works trains were required. The points
were constructed in the car park prior to the weekend. They were
built in three sections due to the length required for high speed
points.
During the shutdown on
Saturday, work was also carried out on the bridge over Mt.Alexander Rd.
at Essendon to remove the old decking form where the third track used to
lie.
Trains terminating at Essendon
Approximately a month before the works,
Platform 1 had lines painted on it , and it was generally given a good
clean up. On Friday 23rd June (the day prior), there were workmen
filling potholes in the platform, and generally levelling the surface.
 |
A Comeng set waits to depart from
Platform 1 at Essendon on Saturday 24-06-00 |
Due to the way trains
are timetabled, they usually cross at Essendon, this meant that PL3 was
used for arrivals, whilst the PL1 was used for departures due to it's
proximity to the bus stops. Once the train departed PL1, the train
in PL3 shunted out toward the city, and used the points at the southern
end to switch tracks to run back into PL1. This is slow, as the
driver had to swap ends twice, but the points at the Northern end could
not be used to swap tracks due to the trackwork on the bridge.
September
2000
 |
New Signal bay
and computer room had all the pre-fab walls put up on the 16-09-00
- at the down end of down platform at BMS (- info and photo
courtesy Chris Gordon)
|
Also by now it was
noted that most, if not all, of the new (concrete) signal bases had been
installed. There were also large track sections lying on the area
where "sidings C" are, possibly the new second set of HS
points.
By the 11-09-00 the refuge siding was back in use,
and all the new drainage works appear to be mostly complete.
October
2000
Saturday October 14
The new signal bay
appears mostly complete, with an air conditioner now installed, it
appears it is just finishing touches as far as the structure itself is
concerned.
Work has been started on the new signals and it
appears that they are working from the North, with the new distant
signal installed about 200m north of the old one and two others to the
north of the station, as well as two on the north ends of the station
platforms. Masts are up for most other
signals now, except that on the goods line along side Pascoe Vale
Rd. All installed lamps are turned to face at right angles to the
track.
 |
New Up Broadmeadows
Repeater with old Distant signals in the distance. |
 |
Signals North of Barry
Road bridge on the down. |
 |
Signals opposite
McDonalds (Maccas is behind the trains to the right) |
 |
Looking North West at
the end of the station platforms with new and old signals.
(Station buildings are to the left on the other side |
Second
set of points
SAT 11th - SUN 12th November 2000
Following info courtesy Chris
Gordon
 |
The new down end high speed points were installed over 11-12th. Down suburban trains terminated in the
down platform (PL2) with a baulk provided 1/2 way along the platform
track.
The Refuge
Siding was be out of use from Friday 10-11-00 until the new
interlocking was commissioned over 18-19 November. Siding
"B" was out of use for 11-12 Nov only. Only siding
"A" was available (holds one six car train only). |
All VLP and Freight trains did not run for the duration of the weekend. |
New Signalling
Operational
SAT 18th - SUN 19th November 2000
Following info courtesy Chris
Gordon
The new signals at Broadmeadows will be commissioned
over the weekend of 18/19 November 2000. Work will start on Friday
17-11-00 from 21:00 until 04:00 Monday 20-11-00. The system will
be monitored for the week to iron out any problems.
Freight trains will run before and after the works, and there will be no
trains through or at Broadmeadows at all over the weekend. Suburban
trains will terminate at Essendon.
Completed
Works
After all the works were completed in 2000, an hour or
so was spent at BMS one morning a couple of weeks later...
 |
A Comeng Set pulls into
PL2 |
 |
P22+A79 haul a late
running Tocumwal goods over the new HS points (at the City/South
End) into PL1, to pass a suburban train in PL2 (main PL) |
 |
A Hitachi Set in PL2 |
 |
A citybound VLP train
behind N452 waits at the new signals on PL1 |
 |
N464 in PL2 |
 |
The new signal box at
the North End of the station. |