: Third track between Mitcham and Blackburn (I guess they mean Box Hill and
: Ringwood?)
No they mean Blackburn to Mitcham, going through Laburnam and Heatherdale
with 3 tracks would require thinking and money. (it can be done)
: "flyer" trains to outer suburbs
: What are flyer trains? (do they fly? =)
Like one train overtaking another, like what they currently have between
Box Hill and Richmond with local stopping trains and express train from
Ringwood (and beyond), also Moorabbin - Caulfield with express train from
Frankston and local stopping trains from Mordialloc.
A third line between Blackburn and Mitcham would only cost about $30 million.
they should spend a little extra and third track all the way from Box Hill
to Ringwood and get rid of the 6 level crossings at the same time.
(I better stop dreaming now, it won't happen)
So say $70 Million for all these works or $255 million for the freeway
to Ringwood (which is only about 3km).
--
Chris Gordon
http://www.ecr.mu.oz.au/~cmgord