Ian Larcher <metalastic@ozemail.com.au> wrote in message
WqRT3.390$46.2759@ozemail.com.au">news:WqRT3.390$46.2759@ozemail.com.au...
> Work has commenced in the section Kandos-Mudgee. RSA units 4819/4827 and
11
> NDAF wagons are presently being used to unload a mixture of timber & steel
> sleepers. Work today was between Lue & Mt Knowles/Mt Frome. Tomorrow
should
> be Lue area & back towards Rylstone.
>
> Sleepers are stockpiled at Lue and loaded into the NDAF's for unloading as
> required. The train today was unloaded by midday when the units were shut
> down & crew returned to Lithgow. Train reloaded ready for 0800 start
> tomorrow.
>
>