Re: Adelaide Hills tonnage limit reduced



No surprise there, after all, the SAR only hauled a
fraction of that, they did not even think about running
their 900 class tripled.! .....took ANR to do that.

Bypassing the Adelaide Hills as proposed by the now
dead federally owned ANR/AN many years ago is the
answer, but we have no pollies willing to do that.

....Tell



>"Peter J. Vincent" <pjv101@netspace.com.au> wrote:

> Train tonnage has been reduced to 4000t per train for trains through the
> adelaide hills ( and presumably the ADE-MEL corridor ).
> 
> This has been caused by significant delays to train running due to
> failure of automatics couplings ( "pulled autos" ).