Re: Platform 1, Flinders Street
: * The concreting on this platform took no more than two weeks in total,
: from the closing date, most of the other platforms took at least a month or
: more.
Plus all the other times platform 1 has been closed, the number of times
in the last 2 years that Clifton Hill trains have gone from platform 14
(some of the time was when platform 1 was in use by Burnley trains).
: Is platform 14 going to remain after Flinders Street has finally been
: finished (seems to be taking them forever)? At the moment, Platform 14
: looks much out of place, and more an afterthought. The space that platform
: 14 occupies looks much like it could become a second track providing direct
: access to the Jolimont line from Platform 1 (rahter than the maze it goes
: through now to do it).
Yes, it will be an emergancy platform.
: There is something being built inbetween platform 14 and Filnders Street
: itself, beneath the federation square, does anyone know what this is?
It is for Fed. Square. There is also other stuff at the end of platform
4/5 and 7/8 and 12/13.
: Regards
: Michael
--
Chris Gordon