[Date Prev][Date Next][Thread Prev][Thread Next][Date Index][Thread Index]

Re: Construction of track - help with costs please





Andrew Robson wrote:

> I need some help to work out the cost of constructing two sections of track.
>
> The first would be 300 metres of curved 3'6" track, with three sets of
> points, to form a wye across the throat of an existing junction.  This would
> allow trains to leave a down line, cross an up line, then travel in a wye
> across the throat of an existing junction (in the opposite direction) from
> the up line.
>
> Existing
> =================================>>>
>
> <<<=================================
>                                                            //
>                                                            ll
>                                                            ll
>                                                            ll
>                                                            ll
>
> Required
> =================================>>>
>                  \\
> <<<=================================
>                         \\                                 //
>                           \\                               ll
>                             \\                             ll
>                               \\                           ll
>                                  \\                        ll
>                                    \\                      ll
>                                      \\                    ll
>                                          \\                ll
>                                             \\             ll
>                                                \\          ll
>                                                   \\       ll
>                                                        \\  ll
>                                                           \ll
>                                                            ll
>
> The second would be a set of points leading of an existing 3'6" line, with
> about 500 metres of track, and two sets of points forming a passing loop to
> facilitate locomotive escape from the branch line.
>
> Existing
> ===================================
>
> Required
>                           ===============
>                         //                                 \\
>             =============================
>           //
>          //
>         //
> <<===================================>>>
> I don't want to go to the state government railway just yet for various
> reasons, and am wondering if anyone inside or outside Queensland with
> experience of this or similar guages can help me out please with realistic
> cost estimates for Australian construction?
>
> The track would need to be capable of handling heavy wagons.
>
> If you can help, please post here or email me directly on
> ajrobson@gil.com.au
>
> Andrew
> Brisbane

--


Try approx $0.5M...it depends very much on signalling required, maybe uo to $1M
with signalling involved.

Bruce L. Greening
bgreeni@ibm.net