[Date Prev][Date Next][Thread Prev][Thread Next][Date Index][Thread Index]
Re: Swanston Street Works
>Additional comments from David Langberg, whilst talking to a Swanston
>Trams employee overseeing the work:
>This is the 2nd last major infrastructure project from Swanston Trams, any
>further work will be undertaken by the new private company aftre June.
>(The next project will be the High St & Chapel St intersection)
>
>The replacement of the Swanston St / Franklin St points were scheduled for
>a while ago, but was cancelled at the last minute. It was done on the
>weekend just gone becuase of the Grand Pirx next weekend, and this
>intersection was regarded as "a major problem intersection". i.e. If
>something is going to stuff up while the Grand Prix is on, it would be a
>tram derailed at this intersection.
Hi there
Swanston Trams are also going to do Elizabeth & Victoria curves on the
57 route on the 27/3 & 28/3/99
Regards
Anthony Tubbs
Swanston Trams