Re: Sydney Airport LInk




R F Horgan <rhorgan@idx.com.au> wrote in message
376c7c43.0@news1.idx.com.au">news:376c7c43.0@news1.idx.com.au...
> Does anybody have any up to date info on how construction of this project
is
> progressing

Track from Central to Green Square is basically in place, track from Turella
to Wolli Creek is in place, although no ballast has been placed within the
tunnel yet. The new track work from Turella stops just short of a vehicle
access point into the tunnel right below the up Illawarra local line. In
will continue to be laid from about 3 weeks time. Wolli Creek, International
and Domestic terminal stations are well advanced, with wiring, wall lining
painting etc to be completed.--
Robert Parnell
Rail Access/Railcom Technician, Electronics Enthusiast,
Lachlan Valley Railway Director,  NSW HO scale railway modeller>