Stage 3 was finished at Ringwood last weekend (10/11 April) all
points (expect the sidings) are now motorised (and renewed, for
the ones that were already motorised) there remains a connection
between the single compound (down end) and the points at the up
points (going to be build with concrete sleepers)

Basically everything at Ringwood from Post 2 & L780 to H827 & L878
points, signals, trip levers, track circuits have been or will be
replaced (inculding Bedford Road Level crossing)

I have updated my Ringwood page with some pictures of the buildings
(before they are burnt down, after the application was turned down)
The latest signalling diagram, stage 2 & 3 works.

                                            
http://www.ecr.mu.oz.au/~cmgord/trains/ringwood