Jolimont Rationalisation Project (JRP)



Closure of the Flinders Street Yard:

As new sites become available closure of that part at Flinders Street.
New timetable to be implemented on 8 February 1998 to cater for the full closure of FS yard.

Flinders Street - Richmond track Simplification and upgrade
With the removal of the sidings at FS the track will be simplified to 12 main lines each with a running speed of 80 km/h.  This will be completed by the end of 1999 in 6 stages.

  1. 1    (15 - 30 Nov. 1997)   A continuous occupation of the four Burnley group lines and platform 2 & 3 at FS.  An altered timetable for this period has been developed.
  2. 2    (21 Mar - 13 Apr 1998)    A continuous occupation of the four Caulfield group lines and platform 6 & 7 at FS.  An altered timetable for this period is currently being developed.
  3. 3    (July, 1998)    Same with the Special lines and Plat 8 & 9 at FS.
  4. 4    (Cot, 1998)    Same with the Sandringham lines and Plat 12 & 13 at FS.
  5. 5    (Dec, 1998)    Same with the Clifton Hill lines and Plat 14 at FS.
  6. 6    (Mar, 1998)    Same with the four Burnley lines (again).
 

                            Chris Gordon