Jolimont Rationalisation Project (JRP)
Closure of the Flinders Street Yard:
-
All train stabling sidings throughout FS yard will be decommissioned by
March 1997.
-
New maintenance facilities at North Melbourne to be completed by the end
of October.
-
New siding at Burnley for 6 trains - 3 November 1997
-
Additional sidings at Camberwell for 4 trains - 2 December 1997
-
Maintenance facility at Westall, with stabling for 7 trains - 29 January
1998
-
Maintenance facility at Bayswater, with stabling for 2 trains - 12 February
1998
-
The light Repair centers (LRC) at Westall and Bayswater to be equipped
like the Macaulay LRC.
-
Cleaning like at North Melbourne also at Burnley.
As new sites become available closure of that part at Flinders Street.
New timetable to be implemented on 8 February 1998 to cater for the
full closure of FS yard.
Flinders Street - Richmond track Simplification and upgrade
With the removal of the sidings at FS the track will be simplified
to 12 main lines each with a running speed of 80 km/h. This will
be completed by the end of 1999 in 6 stages.
-
1 (15 - 30 Nov. 1997) A continuous occupation
of the four Burnley group lines and platform 2 & 3 at FS. An
altered timetable for this period has been developed.
-
2 (21 Mar - 13 Apr 1998) A continuous
occupation of the four Caulfield group lines and platform 6 & 7 at
FS. An altered timetable for this period is currently being developed.
-
3 (July, 1998) Same with the Special
lines and Plat 8 & 9 at FS.
-
4 (Cot, 1998) Same with the Sandringham
lines and Plat 12 & 13 at FS.
-
5 (Dec, 1998) Same with the Clifton
Hill lines and Plat 14 at FS.
-
6 (Mar, 1998) Same with the four Burnley
lines (again).