>The Glenfield via Granville and Hornsby via Strathfield services were
simply
>cancelled. I *suspect* that 15 trains / hour is considered to be the
>practical maximum to run on one pair of tracks through Strathfield.
>
This seems a bit odd, it's only one train every 4 minutes. I would have
thought 20 trains per hour would be the maximum, one every 3 minutes, or
better (although you need some slack for late running, etc). What is it
normally during the peak hour?