[Date Prev][Date Next][Thread Prev][Thread Next][Date Index][Thread Index]

thre Start of the Metro Light Rail Extension]





EDWARD CROFT wrote:

> Dear Mr Barr-David,
>
> I confirm that preliminary work has commenced on the Light Rail Extension
> from the existing Wentworth Park Stop to the Liliyfield Stop. The
> preliminary work has included clearing of rubbish and vegetation from the
> track, detail survey, geotechnical invenstion, erection of fencing,
> erection of erosion and sediment control measures and establishment of the
> Contractor's site office at Jubliee park.
>
> The next step is to commence more substantial construction activities such
> as excavation at the five Stop sites, trackwork and foundations for
> overhead wiring system. We are programmed to commence these activities this
> week.
>
> Regards,
>
> Mike Punch