Re: XPTs "run late", "34 percent jump in customer complaints"
TB wrote:
> This is from the Gold Coast Bulletin on Saturday December 5 1998:
>
> Trains run late
>
> COUNTRYLINK trains, including the Murwillumbah XPT, have performed
> below target with 15 percent of services running late in 1998,
> reports State Rail. There was a 34 percent jump in customer
> complaints to 3052.
The October 1998 figures show 84% of CountryLink trains running on time.
Explanation:
"Mechanical failures and speed restrictions once again affected Countrylink's
on-time running. Countrylink is continuing with a program to address these
issues."
On a related note, for the same time period, CityRail Suburban on time running
was 93.8%, and Intercity was 93.1%.
--
David Johnson
CityRail Guard
trainman@ozemail.com.au