[Date Prev][Date Next][Thread Prev][Thread Next][Date Index][Thread Index]

Miscellaneous Melbourne Works 7 to 22 June 2000



Ballast Cleaning 21/22 June

Line Section: Dandenong line (Pilot Freight trains SLW after 1.00)
Occupation: 20.30 to 04.00 on up track and 21.15 to 04.00 on down track
between Springvale and Dandenong
Plant Trains: 1 dirty ballast, 1 clean ballast

Details

21 June  Up track (Noble Park) Up end of pit to  Heatherton Rd = 350m
    Discharge into train

22 June  Up Track Surfacing gang to tamp previous cut to final line and
level

Machine Stable: Dandenong

----------------------------------------------------------------------

Ballast Cleaning 19/20 June

Line Section: Caulfield Throughs
Occupation: 20.30 to 04.00 each day on Up and Down Caulfield through's
between Richmond and Caulfield
Plant Trains: 2 dirty ballast, 2 clean ballast

Details

19/20 June Up Caulfield Through (Hawksburn) Mast 142 to
  Mast 154 = 320m
  Discharge into train

Machine Stable: Caulfield

----------------------------------------------------------------------

Ballast Cleaning 7/8 and 14/15 June

Line Section: Flinders St to Richmond
Occupation: 20.30 to 04.00 each day on Up Burnley & Down Caulfield local
Plant Trains: 4 dirty ballast, 4 clean ballast

Details

7/8 June Up Burnley Local (Flinders St) Mast 61/22+32m to
  Points 265d = 250m
  Discharge into train

14/15 June Down Caulfield local (Flinders St) Mast 61/22 + 32m to
  Mast 47/6c = 250m
  Discharge into train

16 June  Complete final tamp

Machine Stable: Burnley

Sightings:

Thur 8 June 2000 Burnley @ 01.00 D ???? GN377 18 GHBA ballast

Wed 14 June 2000 Richmond Junction @ 11.30 Y168+dirty ballast+GN375+GN345