Miscellaneous Melbourne Works 7 to 22 June 2000
Ballast Cleaning 21/22 June
Line Section: Dandenong line (Pilot Freight trains SLW after 1.00)
Occupation: 20.30 to 04.00 on up track and 21.15 to 04.00 on down track
between Springvale and Dandenong
Plant Trains: 1 dirty ballast, 1 clean ballast
Details
21 June Up track (Noble Park) Up end of pit to Heatherton Rd = 350m
Discharge into train
22 June Up Track Surfacing gang to tamp previous cut to final line and
level
Machine Stable: Dandenong
----------------------------------------------------------------------
Ballast Cleaning 19/20 June
Line Section: Caulfield Throughs
Occupation: 20.30 to 04.00 each day on Up and Down Caulfield through's
between Richmond and Caulfield
Plant Trains: 2 dirty ballast, 2 clean ballast
Details
19/20 June Up Caulfield Through (Hawksburn) Mast 142 to
Mast 154 = 320m
Discharge into train
Machine Stable: Caulfield
----------------------------------------------------------------------
Ballast Cleaning 7/8 and 14/15 June
Line Section: Flinders St to Richmond
Occupation: 20.30 to 04.00 each day on Up Burnley & Down Caulfield local
Plant Trains: 4 dirty ballast, 4 clean ballast
Details
7/8 June Up Burnley Local (Flinders St) Mast 61/22+32m to
Points 265d = 250m
Discharge into train
14/15 June Down Caulfield local (Flinders St) Mast 61/22 + 32m to
Mast 47/6c = 250m
Discharge into train
16 June Complete final tamp
Machine Stable: Burnley
Sightings:
Thur 8 June 2000 Burnley @ 01.00 D ???? GN377 18 GHBA ballast
Wed 14 June 2000 Richmond Junction @ 11.30 Y168+dirty ballast+GN375+GN345